Profitable plant operation is inconceivable without a secure supply of spare parts. Capital-intensive facilities in waste management in particular depend on maximum availability in order to be able to operate economically in the long term. Against the background of increasing capacity bottlenecks, RZR Herten has invested in the reorganization of spare parts logistics. The solution developed by MALORG Consulting takes into account necessary expansion measures as well as the continued productive use of existing storage facilities.
Success stories
Concept planning for the reorganization of the spare parts warehouse
27. May 2022, Reading time: 1 min 51 second
Initial situation for the project
- grown structures lead to the fact that existing areas as well as applied and in the meantime outdated storage and conveying technology reach their capacity limits
- increasing bottlenecks in material flow
- Development of a concept for the reorganization of spare parts logistics
As-is analysis reveals optimization potential
- Consideration of the integration of a new incoming and outgoing goods office
- Derivation of optimization potentials when recording the actual processes
Conversion from pallet warehouse to block storage
- Solution: optimized space utilization concept with consideration of partial use of existing technologies
- Four-way stacker as new investment for the conveyor technology between incoming and outgoing goods and the storage areas