The logistics service provider PFENNIG LOGISTICS built a new distribution warehouse for its customer Kraft Foods at the Heddesheim site, including an electric pallet floor conveyor, an electric overhead conveyor and a deep-freeze warehouse. MALORG Consulting supported the customer’s project team in the commissioning and start-up management of the warehouse and subsequently took over the preparation of the WMS specifications as well as the evaluation of the picking process.
Success stories
Commissioning and start-up management for a new distribution warehouse
27. May 2022, Reading time: 1 min 49 second
Project Management
- Analysis of layout and specifications
- Planning of commissioning, definition of tests, detailing of schedule
- Goal: Managing the commissioning phase without unexpected negative events
- Risk management
Progress control and spare parts selection
- Ensuring the supply of spare parts
- Compilation of an optimized selection of spare parts
- Identification and presentation of weak points
Acceptance planning and implementation
- Definition of acceptance tests and performance conditions
- Performing acceptance and performance tests
- Determination and evaluation of relevant key figures
Delivered: Performance, deadlines and costs
- Stable start-up of the electric pallet conveyor in compliance with performance, deadlines and cost targets
- Supervision of the preparation of specifications and requirements for the electric overhead conveyor for order picking